The output is suitable for generating a timeline with data points for each time a task enters or leaves a column. The column_metrics data set looks like this: | project_phid | column_phid | task_id | ts_begin (unix ts) | ts_end (unix ts) | duration (seconds) | |--------------|-------------|---------|--------------------------|-----------------------|------------------------| | PHID-PROJ-1 | PHID-PCOL-1 | 123456 | Time task entered column | Time task left column | How long task remained | We can also derive another type of metrics from this same dataset - to calculate global workboard metrics and task-specific metrics we simply summarize the above data. * Each task will have a duration value for each on the workboard. ** the lead time for the task is the duration in default colum ** cycle time is total off all durations except for default column * Global workboard metrics are the mean of all durations...